Al AIn Hospital_094859795.jpg
17,000m2
Wet Area
37,000m2
Roof
Al AIn Hospital_094859795.jpg

Highlights

Stakeholders

Client

Musanada

Consultant

Obermeyer Engineering/Allen & Sheriff

Main Contractor

Arabtec San Jose JV



Objectives

Waterproofing of a steel roof with a high number of solar stand penetrations, each requiring individual detailing and sealing

 

Waterproofing system carrying a 20-year warranty

Solution

Wet areas — 17,000 m² of cementitious coating

 

Roof — 37,000 m² of SBS membrane and 12,000 m² of hot rubberised asphalt monolithic membrane, with extruded polystyrene insulation